Long Thanh Airport Eyes Dec 24 Opening, East Wing Waits to 2027

Under ACV's plan sent to the State Inspection Council, Long Thanh airport is due to start commercial operations at 00:00 on 24 December, but the passenger terminal's east wing is only fully accepted in March 2027 and the cargo terminal in early May 2027.

Long Thanh Airport Eyes Dec 24 Opening, East Wing Waits to 2027
Phương Nam

Phương Nam

Policy & Infrastructure

Long Thanh airport is due to receive commercial flights before its passenger terminal has been fully accepted. According to the plan that Airports Corporation of Vietnam (ACV) has just sent to the State Inspection Council, the terminal's west wing and central zone receive conditional acceptance in December, while the east wing is expected to be fully accepted only in March 2027. ACV has also announced that the airport is scheduled to begin commercial operations at 00:00 on 24 December.Dân trí

So 24 December is a partial opening. After that date the airport will operate and build at the same time, and acceptance of items finished after December runs on to May 2027.Dân trí This article follows that acceptance calendar. The milestones simply come one after another on a schedule. They are not a causal chain, and each one is the project owner's plan, not work already done.

ACV's acceptance schedule, 15 November 2026 to 1 May 2027

Milestones before 24 December

The airfield comes first, because aircraft need it first. Under ACV's plan, package 4.12 (the second runway) receives conditional acceptance on 15 November, and package 4.6 (runway, taxiways and aircraft apron) on 29 November.Dân trí

The cargo terminal frame follows. In package 7.8, the items prioritised for December commercial operations (structure, roof, outer walls, electrical and medium-voltage rooms) are to be accepted in stages between 25 and 30 November.Dân trí

Mid-December is the turn of the internal roads and a car park. Package 4.8 (internal transport and technical infrastructure) is due conditional acceptance on 15 December. In package 11.5, car park P2, the pedestrian bridge, infrastructure and mechanical-electrical systems are due between 15 and 18 December.Dân trí

Last comes the partial opening of the passenger terminal. For package 5.10, all construction and equipment in the west wing and central zone receive conditional acceptance in December.

What passengers can use in the first months

According to the ACV plan cited by Người Quan Sát on 15 November, ACV is prioritising the west wing and central zone and setting up 4 check-in islands for the early phase. From December 2026 to March 2027 these two areas are expected to handle both domestic and international flights, at about 20–30 flights a day.Người Quan Sát

Passenger terminal diagram: west wing and central zone accepted conditionally in December 2026, east wing in March 2027

The two airlines taking part at the start are Vietnam Airlines and Vietjet Air, with registered output equal to roughly 6–10% of design capacity. The maximum scenario is 366 flights a week, made up of 322 domestic and 44 international flights.Người Quan Sát

For scale, phase 1 design capacity is 25 million passengers and 1.2 million tons of cargo a year.Người Quan Sát In the early months the airport will run at a small share of that capacity, inside part of the terminal.

Inside the Long Thanh passenger terminal, with the steel and glass roof still being completed

Milestones into 2027

The acceptance calendar runs well past 24 December:

  • 24 December to 1 May 2027: the facade, interiors, mechanical-electrical and IT systems of the cargo terminal (package 7.8) are finished after December and accepted within this window.
  • March 2027: the passenger terminal's east wing is fully accepted. In the same month, the remaining items of package 4.8, the rest of package 4.11 (wastewater treatment) and package 5.11 (IT systems) are due for completion.
  • 20 April 2027: car park P1 and the central block of package 11.5 are accepted.Dân trí

In other words, in the early months passengers use a terminal whose east wing is not yet finished and a car park with only P2, while cargo moves through a terminal whose facade and mechanical-electrical work is still under way.

Work remaining on the four lagging packages

The calendar matches the progress figures cited by the Ministry of Construction. By these figures, package 4.8 has completed over 82% of its volume, package 5.10 over 87%, package 7.8 only over 50% and package 11.5 nearly 45%. ACV's periodic reports show that monthly progress on these packages is only 1–5 percentage points.Dân trí

Work completed on the four lagging packages: 5.10 over 87%, 4.8 over 82%, 7.8 over 50%, 11.5 nearly 45%

Package 11.5 still has more than half its work left, and progress is a few percentage points a month. The Ministry singled out the construction items of packages 7.8 and 11.5 and the equipment items of package 5.10.Dân trí Deputy Minister of Construction Phạm Minh Hà concluded at the progress review for component project 3 that the Ministry recognises ACV has made great efforts in directing contractors, but the remaining volume in many packages is still very large and it will be hard to finish these items in 2026.Dân trí If they are not done within the year, the project may have to request an extension, and the Ministry asked ACV to report promptly to the competent authority to adjust the project as regulations require. It also asked ACV to assess objectively whether packages 5.10, 4.8, 7.8 and 11.5 can be completed, with concrete measures for contractors to meet their commitments.

24 December still awaits licensing

The 24 December date is the one ACV has announced. According to the Ministry of Construction, as published by Người Quan Sát on 17 November, before aviation-specific licensing can begin the airport must complete project acceptance and fire-safety acceptance, hold an environmental permit, and have its aviation security programme approved. Only then will the Civil Aviation Authority issue licences in one batch to ACV, Vietnam Air Traffic Management Corporation and the service providers.Người Quan Sát

The Civil Aviation Authority is working with ACV and the air traffic corporation to prepare aeronautical information announcements, ready in case the competent authority decides to put the airport into operation from 24 December.Người Quan Sát Put differently, the date is being prepared procedurally. It is not yet a licensed date.

On the government side, Standing Deputy Prime Minister Phạm Gia Túc tasked the Ministry of Construction with reviewing the options and conditions needed to put the airport into operation before 31 December. He also asked ACV and the Đồng Nai city People's Committee to study measures that guarantee security and safety and look after housing and meals for workers while the airport is operating and under construction at once.Dân trí

What shareholders should read from this calendar

For ACV shareholders, the schedule shows two separate rhythms. The airport starts operating at the end of the year, at a scale of a few dozen flights a day and in only part of the terminal. Most of the unfinished investment volume in the four lagging packages will be completed in 2027, with the last cargo terminal milestone on 1 May 2027. A sensible reading is to treat 24 December as the start of a gradual ramp-up, not the day the airport reaches full capability.

For listed contractors with work on packages 7.8 and 11.5, the plan shows the remaining work running into next year. This article offers no view on the share price of ACV or any contractor.

What to watch next

The nearest date is 18 November. Under the Ministry of Construction's 8 November request, ACV works with the Civil Aviation Authority on an operating plan for phase 1, and the Authority sends its review results before 18 November so the Ministry can hold a meeting to review preparations for operations in November.Dân trí That meeting will show how the early-phase operating plan is settled. After it, the acceptance dates of 29 November for the airfield and 15 December for the internal roads are two tests of whether ACV's schedule holds.

Tags:ACVlong thanh airportinfrastructureproject acceptanceministry of construction
Phương Nam

Phương Nam

Policy & Infrastructure

Reads policy to find investment opportunities before the market reacts.