Long Thanh: Bid-by-Bid Probes Now Drive the Fix

Notice 601 asks the Ministry of Public Security to establish violations package by package and item by item, and uses those findings as the basis for remedies. The opening date now runs through a chain of files, with the nearest deadlines on 5 and 10 December.

Long Thanh: Bid-by-Bid Probes Now Drive the Fix
Phương Nam

Phương Nam

Policy & Infrastructure

On 28 November the Government Office issued Notice No. 601/TB-VPCP, relaying the conclusions of Standing Deputy Prime Minister Pham Gia Tuc from a 25 November meeting on Phase 1 of Long Thanh International Airport. The notice hands out tasks to several ministries, two localities and three companies. One line shapes how the whole project moves forward: the Ministry of Public Security is asked to speed up its investigation and establish responsibility and the degree of violation at each bid package and each work item, and the results become the basis for agencies to draft remedies under the Politburo's Conclusion 24-KL/TW.Fireant

In other words, the date Long Thanh can open no longer depends only on the construction work left on site. It also runs through a chain of files: clarifying violations, inspecting quality, applying a special mechanism to individual items where needed, acceptance, and only then aviation licensing. This post follows that chain.

From a flawed work item to an operating licence

Why the investigation comes before the fix

According to a report from Airports Corporation of Vietnam (ACV), cited in Notice 601, the project is stuck on acceptance and payment because some procedures were not carried out properly by the investor and contractors. Resolving that requires asking the competent authority to consider special mechanisms and policies.Fireant

The legal frame is Conclusion 24-KL/TW of 13 April 2026 on continuing to unblock long-stalled projects. The Politburo approved the principle of resolving a project's obstacles at the same time as handling the responsibility of the collectives and individuals who violated rules, with three conditions: no legalising of violations, no creation of new ones, and a plan to remedy damage.Fireant

"At the same time" means the project does not have to wait for a trial to finish. Yet the condition of not legalising violations forces decision-makers to know how serious a defect is, and who is responsible, before accepting that item through a separate mechanism. That is why Notice 601 makes the degree of violation at each package an input to the remedy. The Standing Deputy Prime Minister also asked that the process define each agency's responsibility and authority, not legitimise violations, and guarantee absolute technical safety.Fireant

On the number of people prosecuted, Nguoi Quan Sat on 29 November recalled that 31 defendants have been charged in the case involving ACV and related units.Người Quan Sát The Ministry of Public Security disclosed that figure in July 2026; it is not new in Notice 601.

Standing Deputy Prime Minister Pham Gia Tuc speaking at the meeting

From item files to an operating licence

Notice 601 gives the technical work to ACV itself: the company must assess and define the quality of each item that has procedural defects. The ministries of Public Security, Finance, Construction, and Science and Technology are to help ACV set up an inspection council to assess construction equipment, as the company proposes.Fireant

That council was already a bottleneck before the notice. In a Civil Aviation Authority of Vietnam report carried by Dan Tri on 26 November, ACV proposed an inter-agency council to inspect materials whose specifications (manufacturer, model, origin) were changed from the contract. The Ministry of Construction replied on 18 November, but the matter is still unresolved, and the Authority warned it could slow acceptance.Dân trí

Acceptance matters because it unlocks everything after it. The same report says that as airport operator, ACV must complete 20 administrative procedures: 4 are done and 13 more are under way. The remaining 3, including the Airport Certificate, depend on acceptance results for construction, aviation security, fire safety and the environment.Dân trí Notice 601 links exactly these steps: ACV works with the Ministry of Construction to accept completed items, check operating conditions, then process licences and sector-specific approvals.Fireant

ACV's 20 administrative procedures

So a work item with substituted equipment or a skipped procedure has to clear each of these stages before it can count toward the operating licence.

A worker on scaffolding inside the terminal

Two deadlines: 5 and 10 December

The notice sets two specific deadlines. If component project 3 is not completed on schedule, ACV must send the Ministry of Construction a proposal to adjust the schedule and apply special mechanisms before 5 December 2026.Fireant Before that, ACV must review the remaining workload and set dates for completing construction, installing equipment, acceptance, and stand-alone and integrated test runs, and from these fix a specific date for operation.

The Ministry of Construction is the focal point, tasked with handling ACV's proposal in Submission No. 21/TTr-TCTCHKVN of 9 November 2026. If issues remain, the Ministry directs ACV to complete a file covering what the obstacle is, who is responsible, the remedy, the legal basis, who has authority to decide, and a specific list of items to which a special mechanism would apply. The Ministry then finalises a report to the Government and Prime Minister before 10 December 2026, for the competent authority to consider.Fireant

Milestones after Notice 601

The opening date is also tied to the procedure for adjusting the project. At the 25 November meeting ACV proposed pushing the Phase 1 deadline to 2027–2028, whereas under the investment policy approved by the National Assembly, Phase 1 must be completed and put into operation in 2026.Fireant The Civil Aviation Authority noted that a plan to operate part of the airport while finishing the rest must be accompanied by a project adjustment procedure.Dân trí

The money track: advances for contractors, exchange rate awaiting the Ministry of Finance

Alongside the files, Notice 601 opens a track so the site does not stall while the investigation continues. ACV is asked to proactively resolve obstacles in acceptance and payment within its authority, including advances and interim payments consistent with regulations, to secure financing for contractors to keep building.Fireant At the same time, contractors must mobilise maximum labour, machinery and materials, add overtime and work fronts, and ACV is asked to deal with contractors that fall short.

The harder part sits with the Ministry of Finance, which is to lead guidance for ACV on payment, financial mechanisms, price appraisal and the payment exchange rate for imported equipment.CafeF The notice sets no separate deadline for this guidance. On a project with a lot of imported equipment, the rate used at payment directly determines what the investor pays and what contractors receive. Advances keep the site running, but final settlement for imported equipment still depends on the method the Ministry of Finance will lay out.

Two localities also have a role. The People's Committees of Ho Chi Minh City and Dong Nai are to prioritise supplying fuel, materials and labour to contractors when ACV makes specific requests, and to push connecting transport projects and the aircraft fuel pipeline to the airport boundary.Fireant

What falls to Vietnam Airlines, Vietjet and Phase 2

An airport needs more than a runway and a terminal. On component project 4, Notice 601 asks Vietnam Airlines (HVN) and Vietjet (VJC) to speed up construction of the in-flight catering facility, ground-handling and commercial engineering facilities, and aircraft maintenance hangars 1, 3 and 4. The two companies must also soon complete investment procedures for assigned facilities: hangar 2, cargo terminal 2, an express-parcel terminal, and warehouses 5 through 8.Fireant

These facilities link back to project 3. According to the Civil Aviation Authority, access roads and infrastructure links to project 4 are unfinished because they depend heavily on internal-roads package 4.8, which was then only 83.04% complete.Dân trí If the link-up is late, aviation service providers cannot test, pass acceptance or finish their own procedures.

The notice also looks beyond Phase 1: the Ministry of Construction is tasked with reviewing the airport's master plan and proposing to the Prime Minister who should be assigned as investor for Phase 2.Fireant

Long Thanh terminal under construction, runway in front

Two ways to read the notice

The first reading sees tying the fix to the investigation as an extra layer of delay: an item still under investigation cannot yet get a remedy. The second sees it as a route to the fix: thanks to Conclusion 24's "at the same time" principle, the project does not wait for a verdict, only for the degree of violation at each item to be established, while contractors keep getting advances to continue.

The notice leans toward the second reading. It asks the Ministry of Public Security to speed up, tells the ministries to help set up the inspection council, and opens a path for advances. But the investigation itself has no stated deadline, so the real pace of the whole chain still depends on that step.

Milestones to watch

For ACV, the investor of project 3, Notice 601 touches acceptance, payment to contractors and the exchange rate on imported equipment directly. For HVN and VJC, the project 4 items were just assigned for acceleration, and their operating schedule at Long Thanh depends on the date the airport is licensed. For contractors, the advance track determines the cash they receive while the investigation continues.

Our reading: Notice 601 makes the investigation's results the critical path of the project, and the opening date will be hard to separate from how fast each item is clarified. The next documents answer in order. ACV's proposal to the Ministry of Construction before 5 December shows the opening date the investor wants and which items need a special mechanism; the longer that list, the more work depends on investigation results. The Ministry's report before 10 December shows what form that proposal takes when it goes up. And the Ministry of Finance's guidance on the exchange rate will decide the final sum for imported equipment.

Tags:ACVLong Thanh airportNotice 601project acceptanceaviationpublic investment