Under a board resolution dated November 25, 2026, Vinhomes' largest urban area in southern Hanoi was renamed the International Sports Centre Urban Area - Vinhomes Global Centre. Its scale was adjusted to about 9,139.2 ha, and the whole project is now expected to be completed in Q4 2036.CafeF Counted from the December 19, 2025 groundbreaking, that is a stretch of almost 11 years.
The plans behind a project this size only make sense once they sit on a timeline. This post walks through the project's milestones in date order, so that anyone holding VHM shares, or thinking of buying a home in the area, can see where the project stands on its own calendar.

December 19, 2025: groundbreaking as the Olympic Sports Urban Area
Work began on December 19, 2025, with an initial scale of about 9,171 ha and a planned population of about 751,000.Mekong ASEAN The site covers 11 communes of Hanoi, including Dai Thanh, Ngoc Hoi, Thuong Tin, Thanh Oai and Dan Hoa.CafeF
The area is zoned into four functional districts: a transit-oriented district around Ngoc Hoi station, a sports district, a tourism district and a sports complex.Dân trí Zone A covers about 1,858 ha. Zone B covers about 3,000 ha and is home to the VinFast - Trong Dong stadium, designed for 135,000 seats.Người đưa tin

May 2026 and October 21: first rename, then eligibility to raise capital
By May 2026 the project had been renamed the Hanoi International Sports Urban Area.Dân trí
On October 21, the Hanoi Department of Construction announced that the investor consortium was eligible to raise VND 237,000 billion for the housing works in the project.Người đưa tin This milestone touches homebuyers directly. Eligibility to raise capital is the legal condition for a developer to take money from buyers for the housing portion. It does not set a sales launch date or a handover date for any particular zone.
November 6: planned total capital raised
Resolution 61/2026/NQ-HĐQT-VH of November 6, 2026 lifted planned total investment to about VND 1,225,011 billion.CafeF The funding structure is unchanged: consortium equity of at least 15% of total capital, borrowed funds of at most 85%, with Vinhomes contributing 35% of the equity. The actual total capital is for the competent state authority to decide.
The consortium now includes Vinhomes, VinFast Vietnam JSC, Tuong Lai Production, Investment and Development JSC, and Ngoc Quy Trading Investment and Development Co., Ltd.Mekong ASEAN
November 25: second rename and a new completion date
Resolution 63/2026/NQ-HĐQT-VH adjusts three items, and Vinhomes disclosed it on HoSE on November 26.Mekong ASEAN
On the name, this is the second change in roughly half a year. On scale, the area is adjusted to about 9,139.2 ha, compared with about 9,171 ha in the board resolution of March 18, 2026.CafeF The difference is about 32 ha, less than 0.4% of the original area. On schedule, full completion moves from Q4 2035 to Q4 2036.VnExpress

Vinhomes said the specific scale and schedule depend on decisions by the competent state authority, and that items not adjusted remain in force.Mekong ASEAN
The whole project's calendar differs from individual components
Q4 2036 is the date for the whole project, not for every component. Some works inside the area are on much earlier schedules.
By early November 2026, the VinFast - Trong Dong stadium had installed 27,300 tonnes of roof steel out of a total of 65,100 tonnes. Roof lifting in the first zone is expected to start in December 2026, the dome to be finished in May 2027, and the stadium to open from July 2027.Người Quan Sát
The 120 m-wide boulevard linking the stadium to the main roads in southern Hanoi is about 80% complete and is expected to open to traffic on November 30.CafeF

So one project runs on two tempos. The stadium and the main road axis follow a 2027 schedule. The rest of the 9,000-plus hectares, covering housing, tourism and services, stretches to the end of 2036.
Where Vinhomes stands on earnings
The 2036 date should be read next to the company's current results. According to the consolidated Q3 2026 financial statements, Vinhomes posted nine-month net revenue of VND 202,586 billion, four times the same period last year, and net profit of VND 75,059 billion, up 390%. That is already 25% above the VND 60,000 billion profit plan approved by the 2026 shareholders' meeting.Mekong ASEAN

According to Vinhomes, profit came mainly from sales at Vinhomes Green Paradise, Vinhomes Global Gate Ha Long, Vinhomes Ocean Park 2 and Vinhomes Ocean Park 3. Vinhomes Global Centre is not on that list. This year's profit comes from projects already selling, while Global Centre is where Vinhomes is putting in capital and preparing to sell, on the longest schedule of the projects mentioned here.
What the timeline means for two groups of readers
For VHM shareholders. The capital structure has not changed: Vinhomes still contributes 35% of the consortium's equity. What the November 25 resolution changes is the time dimension. That equity, and the sales proceeds flowing back from the project, now run on a calendar that extends to the end of 2036. With planned total capital above VND 1.2 quadrillion, the pace of each zone's launch will decide whether cash returns sooner or later. That is a more useful number to track than the headline capital figure.
For homebuyers in the area. Q4 2036 is the date for full completion, not a substitute for the handover date of any individual unit. The date to read is the handover date in the purchase contract for that specific home, set beside the schedule for the infrastructure and amenities around its zone.
The next document will pin down three numbers
The 9,139.2 ha scale, the Q4 2036 completion date and the roughly VND 1,225,011 billion total capital are all, for now, proposals adopted by Vinhomes' board. Vinhomes itself states that the actual scale, schedule and total capital depend on decisions by the competent state authority.
The approval document from that authority is therefore the signal most worth watching. Until it appears, the calendar to the end of 2036 is the company's plan. Once it is issued, VHM holders and homebuyers will have a legal reference point to set beside the dates in their own contracts.