Long Thanh: Paperwork Must Clear Before Acceptance

ACV reports that component project 3 of Long Thanh airport has completed 88.63% of contract value and asks to move the phase-one deadline to 2027–2028. Three groups of documentation gaps must be resolved before the works can be formally accepted.

Long Thanh: Paperwork Must Clear Before Acceptance
Phương Nam

Phương Nam

Policy & Infrastructure

On the morning of Nov 25, at a working session with Standing Deputy Prime Minister Pham Gia Tuc, Airports Corporation of Vietnam (ACV) said component project 3 of Long Thanh airport cannot be completed in full within 2026 under the contract schedule. Component 3 covers the essential facilities inside the airport, and ACV is the investor. ACV asked the Government to have the Ministry of Construction review the overall schedule and report to the competent authority on adjusting the phase-one deadline to 2027–2028.VnExpress This is the investor's request, not a decision.

Why does a project that has done nearly nine-tenths of the work still need more time? According to ACV's report, the answer has two layers: the remaining construction on several large packages, and documentation gaps that must be cleared before the works can be formally accepted.

Aerial view of the Long Thanh passenger terminal

Nearly nine-tenths of the work, a little over half the money

According to ACV's report at the meeting, the value of work completed on component 3 reached VND 76,953.8 billion, or 88.63% of contract value. Disbursements reached VND 49,507.3 billion, or 57%.FireAnt These figures cover component project 3 only, not ACV's consolidated accounts.

Work completed versus disbursements on component project 3

The two ratios measure different things. The 88.63% figure shows how much work has been produced on site, valued at contract prices. The 57% figure shows how much has actually been paid to contractors. The gap is more than 31 percentage points. At the meeting, the Deputy Prime Minister told ACV to review and clear obstacles in payment so contractors keep the financial resources to continue building.FireAnt

On construction, ACV said the passenger terminal, cargo terminal No. 1, the car park and the airport management system are not expected to be finished or fully tested until June 2027.VnExpress ACV attributed the missed contract schedule to both objective and subjective causes.FireAnt

Steel roof inside the Long Thanh passenger terminal

The second layer: documents must match before sign-off

The part that gets less attention is the documentation gaps ACV reported. According to ACV, all three groups are places where the structure as built does not yet match the approved paperwork.VnExpress

Materials and equipment with a changed manufacturer or origin. Some materials and equipment differ from the contract in manufacturer, brand, type or origin. Ordering, supply and installation took place before the investor approved the change and before the parties signed a contract addendum.

Items built to drawings that do not match the technical design. Some items were built and accepted under approved construction drawings. Those drawings, however, do not conform to the approved technical design, and the technical design has not been amended.

Items built before drawings were approved. Some items went ahead while the construction-drawing design file had not yet been approved.

According to ACV, resolving these gaps is a necessary condition for accepting the completed works and licensing the airport to operate.VnExpress This is the mechanism that keeps a high completion ratio from turning into an opening date. An item that is physically finished is still not counted as complete if its file is not valid. To sign off, each change has to be reviewed, inspected, and then formalized through a contract addendum or an amendment to the technical design.

At the meeting, Deputy Minister of Construction Pham Minh Ha asked ACV to review each change so there is a basis for handling it. For materials and equipment that differ from the contract, he asked for a review of value and cost on top of quality inspection and a check against technical requirements, and said organizing the quality inspection is the investor's responsibility.VnExpress The Deputy Prime Minister demanded a thorough fix of the gaps on the principle of not legalizing violations and not allowing new ones.FireAnt

So the remaining work is not only pouring concrete or installing equipment. Every material change has to pass inspection and a price review, and every design mismatch has to be corrected on paper. The pace of paperwork therefore decides the acceptance date as much as the pace of construction. Other parts of the project are affected too: Nguyen Cong Long, General Director of Vietnam Air Traffic Management Corporation (VATM), said some remaining work on component project 2 depends on progress in completing infrastructure under component 3.VnExpress

Reporting deadlines are not approval dates

The Deputy Prime Minister told ACV to review all remaining work and set clear milestones for construction completion, equipment installation, commissioning, trial operation and the date the airport could open. ACV must report to the Government and send the report to the Ministry of Construction within one week of Nov 25.VnExpress The Ministry of Construction must report to the Government on progress before Dec 10, so the matter can go to the competent authority to consider adjusting the investment policy.FireAnt

Both are deadlines for filing reports, not approval dates. The phase-one deadline is tied to an investment policy the National Assembly approved, so changing it goes through the procedure for adjusting that policy and is not the investor's call. On operations, the Deputy Prime Minister said the airport may open only once it meets all conditions and safety is assured, and told ACV not to trade away quality or structural safety for schedule.VnExpress

Timeline of Long Thanh opening-date milestones

The opening date has moved several times this year. In July, the Civil Aviation Authority of Vietnam said the airport was expected to open officially from Dec 1, 2026. In late October, ACV gave an opening of 00:00 on Dec 24. On Nov 5, the Standing Deputy Prime Minister told the Ministry of Construction to review options and conditions for starting operations before Dec 31, 2026. On Nov 23, ACV still reported a plan to open from Dec 24.VnExpress Earlier changes all moved the first-flight date within 2026. The Nov 25 request differs because it touches the phase-one deadline itself, which sits inside the investment policy, and pushes the large packages' remaining work to mid-2027.

What this means for ACV, HVN and VJC

ACV. Long Thanh is the company's largest investment. The airport covers about 5,000 ha with total capital of nearly USD 16 billion; phase one comprises two runways and a terminal with capacity of 25 million passengers and 1.2 million tonnes of cargo a year.VnExpress While items are unfinished, the cost sits on the balance sheet as construction in progress and is not depreciated. Once in use, the asset starts depreciating and also starts generating revenue.

Forecasts made before the meeting were built on the old schedule. According to KBSV, cited by Người Quan Sát on Nov 21, ACV's depreciation is expected to rise from VND 3,889 billion in 2026 to VND 8,490 billion in 2027, while profit after tax would fall from VND 9,775 billion to VND 7,172 billion.Người Quan Sát If the large packages only finish in mid-2027, both the start of depreciation and the start of revenue from those assets shift with them. The two effects move together, so the net impact on each year's profit has to wait for a new operating schedule. On Nov 25, ACV shares closed at VND 36,600, up 0.27%.

HVN and VJC. At the meeting, representatives of Vietnam Airlines and Vietjet said both carriers are preparing to operate at Long Thanh according to the plan and decisions of the competent authority. The airlines flagged risks to safety and service quality when construction and operations run side by side, and asked that preparation time be taken into account, especially for international flights, since passengers often buy tickets months ahead.FireAnt Vietnam Airlines has registered 72 flights a week and Vietjet plans up to 154 flights a week at Long Thanh through the end of March 2027.Người Quan Sát That schedule needs an opening date announced by the competent authority to be finalized. On Nov 25, HVN rose 2.53% to VND 24,350 and VJC rose 0.36% to VND 137,800, while the VN-Index fell 0.57% to 1,687.45 points.

Contractors. The Deputy Prime Minister told ACV to require contractors to mobilize maximum labor, machinery and funding, work extra shifts, and to resolutely handle, or report to the competent authority for handling, contractors that do not perform to contract.VnExpress The unfinished packages' remaining volume, and the matching payments, will carry into 2027 if the schedule ACV reported holds.

What to watch

The 88.63% completion figure does not tell us the opening date. According to ACV itself, the airport can be licensed only after the works are accepted, and acceptance has to wait for the material and drawing gaps to be resolved. The first commercial flight date therefore now follows two timelines at once: construction of the large packages, and clearing the paperwork.

ACV's report to the Government and the Ministry of Construction, due in the first week of December, will set out milestones for commissioning, trial operation and a possible opening date. The Ministry's report before Dec 10 will show how far the phase-one deadline is proposed to move. If the announced opening date stays in December 2026, it will be a partial opening on an airport still under construction. If it slips into 2027, airline schedules and ACV's 2027 profit forecasts will have to be rebuilt on the new date.