Media reports on November 16, 2026 said the Hanoi People's Committee has issued a decision approving the investment policy for the Binh Minh – Tam Hung multi-purpose urban area, with Vinhomes JSC (HoSE: VHM) as investor. The project covers about 598.2 hectares, with planned total capital of VND 111,137 billion.Người Quan Sát
What sets it apart from Vinhomes' usual commercial townships is the housing mix. Resettlement townhouses take up nearly half of total floor area, and that segment carries the earliest deadline in the decision. This post walks through the project milestone by milestone, from paperwork to homes, and what each one opens up for whom.
August: an investor, then a ceremony
The first legal milestone came on August 26, 2026, when the Hanoi People's Committee issued Decision No. 4577/QD-UBND approving Vinhomes as the project investor.Vietnam Finance Two days later, on the afternoon of August 28, Vinhomes held a groundbreaking ceremony.Người Quan Sát The event was part of a programme of groundbreakings and inaugurations marking the 81st National Day on September 2, and Vinhomes joined the simultaneous start of three projects in Hanoi that day.CafeF
That ceremony needs to be read next to one detail in the new decision. The schedule in the investment-policy approval says construction is expected to start in Q4 2026.Vietnam Finance So two "start" dates now coexist: the August 28 ceremony and the Q4 2026 date in the approved document. Which one marks actual construction will become clearer with the next announcement.

October: the 1/500 plan sets three housing types
On October 15, the 1/500-scale detailed plan for the urban area was approved.Vietnam Finance This is the drawing that says which land becomes which housing, and it defines the three housing types that the investment-policy decision later locked in.
Under the decision, resettlement townhouses take about 3.15 million m² of floor area, or 48.58% of total residential floor area, equal to about 6,747 land plots. Commercial apartments account for about 2.01 million m², or 31.07%. High-rise social housing accounts for about 1.32 million m², or 20.35%, of which 10% of the social housing stock is set aside for rent.Người Quan Sát

Together, resettlement and social housing make up almost 69% of residential floor area. Commercial apartments are under a third. When complete, the area is expected to house more than 105,000 people.CafeF
November: the policy decision fixes capital and profit
The project spans two communes: Tam Hung at about 323.8 hectares and Binh Minh at about 274.4 hectares. The operating term is 50 years, counted from when the State allocates or leases the land or permits a change of land use purpose.Người Quan Sát
On funding, Vinhomes contributes about VND 16,670.55 billion, or 15% of total capital. The remaining roughly VND 94,466.45 billion, or 85%, is expected to be raised from credit institutions and other lawful sources.Người Quan Sát That 15/85 split matches the planned structure of the Hanoi International Sports Urban Area, where Vinhomes' board adopted a resolution on November 6 adjusting expected capital.CafeF
The profit mechanism deserves the closest reading. For social and resettlement housing, the maximum permitted profit is 10% of the construction investment cost of the corresponding housing, excluding land-use fees where applicable. For commercial housing, the cap is 15% of construction investment cost. On top of that, an amount equal to about 10% of the construction cost of the commercial housing is built into sale prices to help lower the cost of social housing, resettlement housing and on-site technical infrastructure. That amount is booked separately and does not count toward the 15% profit.Vietnam Finance

In other words, buyers of commercial apartments here pay a price with a built-in contribution to resettlement and social housing. Vinhomes' profit on all three housing types is capped, and the cap is calculated on construction cost, not on sale price.
Why resettlement comes first
A core goal of the project is to create a pool of resettlement housing to support site clearance for the Hanoi International Sports Urban Area, formerly the Olympic Sports Urban Area, and other key works.Người Quan Sát CafeF adds another group to be housed here: residents affected by the National Highway 1A spatial axis project, from Ring Road 1 to the Cau Gie interchange. That route is about 36.3 km long, crosses 18 wards and communes, and has total capital of nearly VND 162,000 billion.CafeF

Because the housing serves site clearance for other projects, the resettlement part has to finish first. The decision requires priority for technical infrastructure on the resettlement land, aiming to finish in Q4 2026 and no later than early Q1 2027. The whole project is expected to be completed and operating in Q4 2030.Vietnam Finance Having a ready pool of resettlement housing is expected to shorten site-clearance time, cut temporary-housing costs and limit complaints during land recovery.Người Quan Sát
The year-end date should be read precisely: it is the deadline for technical infrastructure on the land. The resettlement pool consists of townhouse plots, so there is still a construction step between receiving a plot and having a home.
What each group gets, and when
Households displaced by the Sports Urban Area, the Highway 1A axis and other key projects have the nearest milestone. About 6,747 townhouse plots form the pool for them, and infrastructure for the resettlement area is due between Q4 2026 and early Q1 2027, only a few months away.
People waiting to buy social housing in Hanoi get about 1.32 million m² of additional floor area in the plan, a tenth of it for rent. Full completion is set for Q4 2030, so this is medium-term supply, not next year's.

For Vinhomes, the project adds planned borrowing and other capital of about VND 94,466 billion to its portfolio south of Hanoi. The total of VND 111,137 billion equals about 8.3% of Vinhomes' consolidated total assets of VND 1,339,199 billion at the end of Q3 2026. It is a planned total investment spread across the schedule to 2030, not an outlay due now. Commercial apartments make up about 31% of residential floor area and carry a 15% profit cap on construction cost. Resettlement and social housing carry a 10% cap. That structure looks more like a project built to a city mandate than a purely commercial one.
Next milestones to watch
The thesis is straightforward: by the decision's own terms, Binh Minh – Tam Hung is first a resettlement housing pool, and the commercial part follows. What to watch is infrastructure on the resettlement land in Q4 2026 to early Q1 2027, together with the construction start under the approved Q4 2026 schedule.
If infrastructure is finished by Q1 2027, the pool of 6,747 plots can start being used for site clearance at the Sports Urban Area and along Highway 1A. If it runs late, land recovery on those projects could slip too, since the decision itself ties the two together. After that, the announcement of prices and purchase conditions for the social housing portion is the next thing buyers will need to read.